2020 Street Reconstruction Project 20-1 – 2.6 miles of local City streets (streets near Norway Street and East River Road, 97th Avenue near Yellowpine Street, Norway Street near 107th and 108th Lane, and Avocet Street near 111th Avenue)
The Contractor for this project is Northdale Construction. The Contractor’s main contact is Kevin Topp at 320-493-7369. The City’s full-time project inspector is Jason Huebscher who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Final cleanup including signing and striping, as well as asphalt pavement joint sawing and sealing, will take place in Area 1 (Avocet Street, 109th and 111th Avenue, 109th Lane, and Xeon Street), Area 3 (97th Avenue near Yellowpine Street), and Area 4 (streets east of East River Road – 89th Avenue, Norway Street, and 86th Avenue) within the next couple of weeks. Final wear course paving will take place on 97th Avenue and Yellowpine Street on Saturday, October 31, 2020.
Final wear course paving is scheduled for the Autumn Knolls neighborhood (Area 2 – Norway Street near 107th Lane and 108th Lane) for Friday, November 6. Boulevard reestablishments throughout Autumn Knolls will take place over the next week and a half. The Contractor will return next spring to perform any additional boulevard repairs, including irrigation repairs that could not be accommodated this year.