Construction Updates

2022 Construction is Underway!

To view an overview map showing planned construction projects throughout the City, such as street reconstruction, road maintenance, park & trail improvements, and Anoka County projects, click here. More information about road maintenance activities is available here.

For more information about City street reconstruction projects 22-1 and 22-2, and to view project locations and letters mailed to affected property owners, visit: www.coonrapidsmn.gov/2022projects.

If you have any questions, you may always email Engineering@coonrapidsmn.gov or call 763-767-6479.

To sign up for email notifications of these weekly updates, click Notify Me and select “Construction Updates.”

2022 Street Reconstruction Project 22-1

4.2 miles of residential streets north of 119th Avenue and east of Round Lake Boulevard, including streets south of 119th Avenue south to 117th Avenue between Kerry Street and Jonquil Street; and the 117th Lane cul-de-sac east of Northdale Boulevard

The Contractor for this project is Douglas-Kerr Underground, LLC. The Contractor’s main contact is Ryan Kerr at 320-679-8937 (office) or 320-515-0046 (cell). The City’s full-time project inspector is Jason Huebscher, who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).

Curb removals will continue to take place next week in the phase 3 area (Wedgewood Drive between Round Lake Boulevard and 119th Avenue including all adjacent side streets). Underground work in phase 3 including miscellaneous valve, hydrant, and storm sewer replacements will be complete on Friday, July 22. Crews will begin to move excess gravel material left from the pavement reclamation process in phase 3 next week.

Remaining curbs in the phase 4 project area (streets north of 119th Avenue and east of Round Lake Boulevard to 121st Avenue including 120th Avenue and Tulip Street) are scheduled to be completed next week.

Asphalt pavement reclamation for the phase 5 combined project area (streets south of 119th Avenue between Kerry and Jonquil Street plus the Marigold and Kerry Street cul-de-sacs north of 119th Avenue plus 117th Lane east of Northdale Blvd) is now scheduled to take place Monday and Tuesday of next week. Miscellaneous valve, hydrant, and storm sewer replacements in phase 5 will begin at the end of next week.

2022 Street Reconstruction Project 22-2 

3.6 miles of residential streets north of 119th Avenue along Zea Street west of Round Lake Boulevard and south of Wedgewood Drive; Zea Street between 119th Avenue and Blackfoot Street; streets south of 119th Avenue and north of Coon Rapids Boulevard between Round Lake Boulevard and Silverod Street

The Contractor for this project is Douglas-Kerr Underground, LLC. The Contractor’s main contact is Ryan Kerr at 320-679-8937 (office) or 320-515-0046 (cell). The City’s full-time project inspector is Zach Pfieffer, who can be contacted any time to respond to specific questions or concerns. Zach can be reached at 763-767-6431 (office) or 612-710-8243 (cell).

Remaining asphalt wear course paving is planned to be completed on the phase 1 streets (streets west of Round Lake Boulevard along Zea Street) early next week.

City staff have received numerous requests to restore yards disturbed by Comcast relocation work – we are forwarding these requests to Comcast staff, who have assured the City they will restore any areas disturbed by their work with topsoil and seed. Comcast restoration crews have indicated all yard and irrigation repairs are planned to be completed for the overall phase 1 project area by Monday, July 25. Remaining temporary wires will be removed and above ground pedestals in need of covers/repairs will be addressed on the phase 1 streets by Comcast within the next two weeks as well.

In the phase 2 area (streets east of Round Lake Blvd and south of 119th Avenue), work on irrigation repairs will continue. Topsoil and sod will be placed in boulevard areas of phase 2 streets as soon as irrigation repairs are completed.

Anoka County Projects 

Foley Blvd (CSAH 11) Railroad Bridge Overpass (between East River Road and Coon Rapids Blvd); 2022 Overlay Program (Phase II, South)

Coon Rapids Blvd (CSAH 1) from 9th Avenue to Mississippi Blvd – Surface Reconditioning/Mill & Overlay

To view the County’s project updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly 

For specific County project questions, contact Chris Osterhus, the County’s Construction Supervisor, at 763-324-3189. 

Watch our Street Reconstruction Videos!   

Watch the City’s street reconstruction videos to learn more about the process! The first addresses frequently asked questions, and the second demonstrates what the process will look like in a Coon Rapids neighborhood.

Visit our website to view them: www.coonrapidsmn.gov/843/Street-Reconstruction

Report It
Share on Facebook
Share on Twitter
Share via Email

Published by the City of Coon Rapids, Minnesota * Copyright 2022
11155 Robinson Drive, Coon Rapids, MN 55433

Powered by
CivicSend - A product of CivicPlus