2022 Construction is Underway!

To view an overview map showing planned construction projects throughout the City, such as street reconstruction, road maintenance, park & trail improvements, and Anoka County projects, click here. More information about road maintenance activities is available here.

For more information about City street reconstruction projects 22-1 and 22-2, and to view project locations and letters mailed to affected property owners, visit: www.coonrapidsmn.gov/2022projects.

If you have any questions, you may always email Engineering@coonrapidsmn.gov or call 763-767-6479.

To sign up for email notifications of these weekly updates, click Notify Me and select “Construction Updates.”

2022 Street Reconstruction Project 22-1

4.2 miles of residential streets north of 119th Avenue and east of Round Lake Boulevard, including streets south of 119th Avenue south to 117th Avenue between Kerry Street and Jonquil Street; and the 117th Lane cul-de-sac east of Northdale Boulevard

The Contractor for this project is Douglas-Kerr Underground, LLC. The Contractor’s main contact is Ryan Kerr at 320-679-8937 (office) or 320-515-0046 (cell). The City’s full-time project inspector is Jason Huebscher, who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).

In the phase 3 area (Wedgewood Drive between Round Lake Boulevard and 119th Avenue including all adjacent side streets) work continues next week with irrigation and boulevard repairs. Cul-de-sacs and side streets along Wedgewood Drive will be paved on Tuesday, August 30 with remaining asphalt driveway restorations in those areas planned for late next week.

Work in the phase 4 area (streets north of 119th Avenue and east of Round Lake Boulevard to 121st Avenue including 120th Avenue and Tulip Street) is mostly complete. Remaining work includes paving the final lift of asphalt wear course pavement, and restorations at Vineyard Park.

Work in the phase 5 area (streets south of 119th Avenue between Kerry and Jonquil Street plus the Marigold and Kerry Street cul-de-sacs north of 119th Avenue and 117th Lane east of Northdale Blvd) includes installation of machine placed curb segments on Tuesday, August 30. Miscellaneous concrete flatwork will be performed in phase 5 late next week. 

2022 Street Reconstruction Project 22-2 

3.6 miles of residential streets north of 119th Avenue along Zea Street west of Round Lake Boulevard and south of Wedgewood Drive; Zea Street between 119th Avenue and Blackfoot Street; streets south of 119th Avenue and north of Coon Rapids Boulevard between Round Lake Boulevard and Silverod Street 

The Contractor for this project is Douglas-Kerr Underground, LLC. The Contractor’s main contact is Ryan Kerr at 320-679-8937 (office) or 320-515-0046 (cell). The City’s full-time project inspector is Zach Pfieffer, who can be contacted any time to respond to specific questions or concerns. Zach can be reached at 763-767-6431 (office) or 612-710-8243 (cell).

Phase 1 (streets west of Round Lake Boulevard along Zea Street) is now complete. Remaining work includes sawing and sealing the new bituminous asphalt pavement surfaces. Property owners should contact the City if there’s any issues with repaired irrigation systems.

City staff have received numerous requests to restore yards disturbed by Comcast relocation work – we are forwarding these requests to Comcast staff, who have assured the City they will restore any areas disturbed by their work with topsoil and seed. Residents should also contact the City if there are any concerns with Comcast relocation work.

In the phase 2 area (streets east of Round Lake Blvd and south of 119th Avenue), remaining work includes the final wear course pavement application on certain streets (expected after the Labor Day weekend), as well as installation of remaining new street lights and street signs. Property owners in the phase 2 areas should contact the City if there’s any issues with repaired irrigation systems.

Street light replacements/LED upgrades within the 22-2 project area are taking place as materials become available and will continue over the next several weeks. All street lights that have been temporarily taken down to accommodate construction will be reinstated.


Anoka County Projects 


Foley Blvd (CSAH 11) Railroad Bridge Overpass (between East River Road and Coon Rapids Blvd); 2022 Overlay Program (Phase II, South)

Coon Rapids Blvd (CSAH 1) from 9th Avenue to Mississippi Blvd – Surface Reconditioning/Mill & Overlay

To view the County’s project updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly 

For specific County project questions, contact Chris Osterhus, the County’s Construction Supervisor, at 763-324-3189.

Watch our Street Reconstruction Videos! 
 

Watch the City’s street reconstruction videos to learn more about the process! The first addresses frequently asked questions, and the second demonstrates what the process will look like in a Coon Rapids neighborhood.

Visit our website to view them: www.coonrapidsmn.gov/843/Street-Reconstruction

Share on Facebook
Share on Twitter
Share via Email

Published by the City of Coon Rapids, Minnesota * Copyright 2022
11155 Robinson Drive, Coon Rapids, MN 55433

Powered by
CivicSend - A product of CivicPlus