2016 Park Redevelopment Projects (Project 15-20)
Woodcrest – All concrete work and trail paving is now complete. Baseball field work will commence next week, including minor grading, placement of AgLime material, and installation of the players’ benches and backstop. Construction of the picnic shelter has commenced and should be completed next week. Prep work for the native planting areas continues, with seeding to occur within two weeks. Final turf restoration and installation of benches and picnic tables will also occur over the next two weeks. It is anticipated that the restroom structure will be installed in September.
Mason – All concrete work and trail paving is now complete. Minor grading activities and turf restoration are anticipated to occur over the next two weeks. Construction of the picnic shelter has commenced and should be completed in approximately one week, with bench and picnic table installation to follow. Prep work for the native planting areas continues, with seeding to occur within two weeks. The playground structure has been scheduled for installation at the beginning of August.
Delta – Site removals are substantially complete on the project, and layout of the new facilities continues. Concrete installation will commence next week for the playground and basketball court. Grading activities will continue on the balance of the site in preparation of trail paving in approximately two weeks.
Pheasant Ridge – All concrete work on the project is complete. Prep work for the native planting areas continues, with seeding to occur within two weeks. Work on the handicap parking area along Pheasant Ridge Drive is also substantially complete, and should be wrapped up next week. Construction of the picnic shelter will occur over the next week, with the installation of benches and picnic tables to follow. The playground structure will be installed in early August.