Street Reconstruction Project 17-3 – Local Streets within Burl Oaks Neighborhoods
The Contractor for this project is North Valley. The Contractor's 24-hour emergency contact is Rodney Riemann at 612-328-7536. Ron Sample is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Ron can be reached at 763-257-3874 (cell).
During the week of September 4, the Contractor will install hand placed curb and gutter on phase 3 area streets (Butternut, Cottonwood, Dogwood, Flintwood, Ilex, Holly, Juniper, Kumquat, and Larch Streets – streets adjacent to 121st Avenue, as well as 123rd Avenue east of Foley Boulevard) on Tuesday and Wednesday. Machine placed curb is planned for these same streets on Thursday.
Temporary mailboxes will be installed where needed for phase 3 area streets on Tuesday. Properties that require temporary mailboxes will be notified in advance.