Street Reconstruction Project 19-3 – 3.3 miles of residential streets
The Contractor for this project is Douglas-Kerr Underground, Inc. The Contractor's main contact is Ryan Kerr, who can be reached at 320-679-8937 (office) or 320-515-0046 (cell). Jason Huebscher is the City’s full-time project inspector, and can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Work during the week of August 5 includes sod installations in the Phase 1A area (Flintwood Street, Goldenrod Street, 114th Avenue, 116th Avenue, Evergreen Street, Evergreen Circle, and 117th Avenue). Storm sewer installations, placing gravel on the streets, and possibly curb and gutter installations are expected to begin in the Phase 1B area where watermain pipe replacements took place (Bridgewater neighborhood consisting of Alder Street, Butternut Street, Cottonwood Street, 116th Avenue, 116th Lane, and 117th Avenue). Existing pavement in Phase 1B on the north half of Bridgewater will be reclaimed.
Valve and hydrant replacements will be completed on Springbrook Drive, and work on the temporary watermain system will begin on the Mississippi Boulevard segment. Concrete work will continue on the west side of Springbrook Drive as well.